Please or Register to create posts and topics.

EPC Subcontract Equipment Risk Sits with the Buyer, Not the Contractor

EPC contractors pass equipment specification and procurement risk to clients through contract language buyers rarely read carefully until something goes wrong.


The EPC contract was a lump sum turnkey arrangement for a mineral processing facility in Mozambique. The client's legal team had negotiated performance guarantees, liquidated damages provisions, and a twelve-month defects liability period. The contract ran to 340 pages. The equipment procurement appendix was fourteen pages, primarily covering approval procedures for major equipment submittals and the client's right to approve the vendor list.

The vendor list approval right created the impression that the client had meaningful control over equipment quality. What the approval right actually governed was which suppliers were eligible to bid for each equipment package. It did not govern: the technical specifications the EPC contractor would issue to those suppliers, the inspection and surveillance the contractor would conduct during manufacturing, or the criteria by which the contractor would evaluate and accept equipment at the factory before shipment.

The contractor's procurement team operated to the contractor's internal procurement standards, which were not provided to the client and were not referenced in the EPC contract. Those standards were adequate for most equipment categories. For the thickener drive units, which were procured from a Chinese manufacturer the client had approved for inclusion on the vendor list, the contractor's procurement standards did not require production surveillance witness points. The client's own procurement policy for equipment of that type would have required them.

What EPC Contract Language Does to Risk

Lump sum EPC contracts transfer schedule and cost risk from the client to the contractor. They do not, by default, transfer equipment quality risk in the way most clients assume. The contractor's obligation is to deliver a facility that meets the performance guarantees specified in the contract. If performance guarantees can be met with equipment that falls short of the client's quality expectations in ways that do not affect guaranteed performance parameters, the contractor has no contractual obligation to meet those expectations.

The thickener drive units failed during the defects liability period. The failure mode was a gearbox bearing arrangement that had been manufactured to a tolerance band the contractor's procurement team had accepted but that the client's own rotating equipment specification would have rejected. The EPC contractor repaired the units under the defects liability clause. The client had no contractual basis to require the contractor to replace the units with equipment meeting the client's specification, because the performance guarantee did not specify the gearbox bearing tolerance.

This pattern recurs in different forms across EPC projects. The client approves a vendor list. The contractor issues specifications to vendors that differ from the client's own equipment standards. Equipment is manufactured and shipped. Problems surface during commissioning or early operation. The contractor makes repairs under the defects liability provision. The client absorbs reliability issues and unplanned maintenance costs after the defects liability period expires.

Closing the Gap

Clients who have learned from EPC equipment procurement failures have added contract language that addresses the gap between vendor list approval and equipment quality accountability. The mechanisms vary:

Client specification primacy: contract language requiring the contractor to procure equipment to the client's equipment specifications rather than the contractor's internal standards. This requires the client to have current, comprehensive equipment specifications, which not all operating companies maintain.

Client inspection rights: explicit rights for the client or client-appointed inspection agencies to witness critical inspection stages at manufacturers, independent of the contractor's own inspection program. Some contractors resist this as interference with their procurement process; others accommodate it as a standard client requirement.

Procurement plan approval: requiring the contractor to submit and obtain client approval for the procurement plan for each major equipment package, including inspection scope, witness point schedule, and acceptance criteria, before issuing purchase orders.

These mechanisms add administrative burden and slow the procurement cycle. They also shift the risk allocation toward the outcome the client actually intends. The alternative is discovering after commissioning that the equipment the contractor procured meets the contract's performance guarantees but does not meet the client's operational reliability expectations, at which point the legal analysis typically confirms the client has limited recourse.

The vendor list approval right in the Mozambique EPC contract gave the client the appearance of equipment procurement control. The actual control over what was manufactured and how it was verified resided with the contractor until problems made the distinction visible.