Please or Register to create posts and topics.

The Force Majeure Clause Was in the Contract. The Event Was Not.

Force majeure clauses in commodity contracts often fail because the specific event is not covered. How traders discover their clause does not protect them.


Every commodity contract has a force majeure clause. Most traders have never read theirs carefully. They assume that if something catastrophic happens — a port closes, a mine floods, a government bans exports — the force majeure clause will excuse their performance. The assumption holds sometimes. It fails more often than traders expect.

The core misunderstanding is what force majeure covers. Force majeure is not a general excuse for non-performance. It is a contractual mechanism that excuses performance only for events specifically listed in the clause or for events that meet a defined threshold of severity and impossibility. If the event is not listed and does not meet the threshold, the clause does not apply. The party that cannot perform is in breach.

The Clause Is a List, Not a Safety Net

Force majeure clauses in commodity contracts typically contain a list of qualifying events: war, civil unrest, natural disaster, fire, flood, epidemic, government action, embargo, strikes, port closure. The list varies by contract. The critical question is whether the specific event that prevents performance falls within the listed categories or within a catch-all provision.

A trader selling chrome ore from South Africa was unable to ship because the Transnet rail line from the mine to Richards Bay was operating at reduced capacity due to cable theft and maintenance backlogs. Rail capacity had declined from approximately 77 million MT per year to roughly 50 million MT, reducing the trader's ability to transport ore to the port within the contract's shipping window. The trader declared force majeure.

The buyer's response was that rail infrastructure degradation was not force majeure. It was not war, natural disaster, government action, or any listed event. It was a chronic operational issue that the trader should have anticipated. The contract's force majeure clause included a catch-all: any other event beyond the reasonable control of the affected party that could not have been reasonably foreseen. The buyer argued that South Africa's rail problems were well-known and therefore foreseeable. The buyer was right.

The arbitration tribunal agreed with the buyer. The rail degradation was a known, ongoing condition, not a sudden, unforeseen event. The trader was in breach. The damages — the buyer's cost of sourcing alternative supply at a higher price — were approximately $280,000.

The operational lesson is precise: force majeure protects against sudden, unforeseen, and insurmountable events. It does not protect against known risks, chronic problems, or conditions that the trader could have mitigated through alternative planning. Rail problems in South Africa, port congestion in India, export permit delays in Indonesia — these are foreseeable conditions that experienced traders plan for, not force majeure events that excuse non-performance.

The Threshold of Impossibility Is Higher Than Most Traders Assume

Even when an event falls within the listed categories, the force majeure clause typically requires that the event renders performance impossible, not merely more difficult or more expensive. Under English law, frustration of contract requires that performance becomes impossible or fundamentally different from what was contemplated. Increased cost or operational difficulty do not qualify.

A wheat trader contracted to sell 30,000 MT FOB Odessa. After the outbreak of conflict, the port was closed. The trader declared force majeure — port closure due to armed conflict, clearly within the listed events. The clause applied. This was genuine force majeure: the port was physically closed, performance was impossible.

Contrast this with a different situation: a fertilizer trader contracted to sell 15,000 MT of urea CIF Brazil. The Suez Canal was temporarily disrupted, and the vessel had to reroute via the Cape of Good Hope, adding 12 days and approximately $350,000 in additional freight cost. The trader argued force majeure. The buyer rejected it. The cargo could still be delivered — it would just take longer and cost more. The canal disruption made performance more expensive, not impossible. The clause did not apply.

The distinction between impossibility and increased cost is where most force majeure claims fail. The trader must prove not that performance became more difficult, but that performance became impossible by any commercially reasonable means. If there is an alternative route, an alternative port, an alternative source — even if more expensive — performance is not impossible.

Traders who rely on force majeure as a contingency plan should examine their clause with three questions. First, is the specific event listed or covered by the catch-all? If it is a known chronic condition, it is likely excluded by the foreseeability requirement. Second, does the event render performance impossible or merely more expensive? If performance is still possible through alternative means, the clause likely does not apply. Third, has the trader taken all reasonable steps to mitigate? Force majeure clauses typically require reasonable mitigation efforts.

The force majeure clause is in every contract because every contract needs one. But it protects against a narrower range of events than most traders assume, and it requires a higher threshold of impossibility than most traders expect. The traders who declare force majeure for events that do not meet the threshold damage their commercial credibility and expose themselves to breach claims. The traders who understand the clause's limits plan for foreseeable disruptions rather than relying on a contractual escape hatch that may not open when they push on it.


Keywords: force majeure clause commodity trade dispute event coverage | force majeure scope commodity contract, FM clause physical trading limitation, commodity contract force majeure failure, specific event force majeure commodity
Words: 877 | Source: Conceptual reframe — structural analysis of commodity trade mechanics | Created: 2026-04-08